RIDEM Consent Decree

Consent Agreement Task  RIDEM_Due DateStatus
Establish procedures to maintain an inventory of municipally‐owned and privately‐owned stmctural controls that discharge to the MS4.31‐Jul‐16Completed.
Submit IDDE Plan to RIDEM7‐Aug‐16Completed.
Complete Asylum Road infiltration project30‐Sep‐16Project completed. Extension was requested and granted to 12‐31‐16. All material reimbursed by RIDEM grant. Labor and equipment provided by City DPW.
Brentwood Avenue. Install two deep sump, leaching CBs.31‐Oct‐16Project completed.
Everglade Avenue. Install two deep sump, leaching CBs.31‐Oct‐16Project completed.
Complete asphalt removal (End‐of‐road retrofits)
Hewett Street
Crockett Street
31‐Oct‐16Project completed.
Cove Avenue. Sediment forebay at end of roadway, install additional riprap.31‐Oct‐16Project completed.
Conduct street sweeping twice annually in specified areas31‐Dec‐16On‐going annually. Completed in 2016.
Oakland Beach Trash Receptacles31‐Dec‐16Acquisition complete. Installation scheduled for Spring 2017.
GIS map of all outfalls, receiving waters, drainage systems, and the contributing drainage areas to the MS4 outfalls in the specified inspection area. The map shall include, but not be limited to, locations of all catch basins, manholes, pipes, culverts, swales, and outfalls located in the specified inspection area. Area A.31‐Dec‐16Completed.
MS4 Annual Report10‐Mar‐17Report in progress.
Complete bio‐retention on Suburban Parkway30‐Jun‐17Project in progress. Contractor began excavation and installation of bioretention media. Shut down for winter. Project will resume in Spring.
Rocky Point Pool Area30‐Sep‐17Pending.
Complete Dry‐weather surveys ‐ Area A31‐Oct‐17In progress
Almy Street. Install two deep sump, leaching CBs upstream of existing CBs.31‐Dec‐17Pending.
Liverpool Street. Install two deep sump, leaching CBs upstream of existing CBs.31‐Dec‐17Pending.
Buckeye Brook Waterway Study31‐Dec‐17 
Edgewater Drive Roadway Abandonment31‐Dec‐17Roadways closed to through traffic.
Midgely Avenue Roadway Abandonment31‐Dec‐17Roadways closed to through traffic.
Lippitt School Demonstration Project31‐Dec‐17Reviewing alternatives for BMP.
GIS map of all outfalls, receiving waters, drainage systems, and the contributing drainage areas to the MS4 outfalls in the specified inspection area. The map shall include, but not be limited to, locations of all catch basins, manholes, pipes, culverts, swales, and outfalls located in the specified inspection area. Area B.31‐Dec‐17Pending.
Complete design and construction of infiltration area at Oakland Beach Avenue and Stender30‐Jun‐18Preliminary plans complete. DPW looking for outside funding. Working with URI Coastal Institute on design and funding.
Complete Dry‐weather surveys ‐ Area B31‐Oct‐18Pending.
Adrian Street. Install two deep sump, leaching CBs upstream of existing CBs.31‐Dec‐18Pending.
Inman Avenue. Install two deep sump, leachinig CBs31‐Dec‐18Pending.
Sundance Street. There are two locations where drainage easements and outfalls are located on recently aquired RIAC property. Detention and/or infiltration could occur at these locations.31‐Dec‐18The City has begun coordinating with RIAC on proposals at these locations. Would need to coordinate with Warwick Planning Department, RIAC, and State Property Commission.
GIS map of all outfalls, receiving waters, drainage systems, and the contributing drainage areas to the MS4 outfalls in the specified inspection area. The map shall include, but not be limited to, locations of all catch basins, manholes, pipes, culverts, swales, and outfalls located in the specified inspection area. Area C.31‐Dec‐18Pending.
Complete design and construction of BMP Oakland Beach Avenue30‐Jun‐19Reviewing alternatives for BMP.
Complete Dry‐weather surveys ‐ Area C31‐Oct‐19Pending.